Works at Galway Hibernians Clubhouse in Bohermore which were abandoned 15 months ago are to restart in three weeks time on August 7th.

The company which had completed about 60 per cent of the construction of the clubhouse went into receivership in spring 2011.

However the contract has now been re-assigned and the works on the 4000 square feet development are to be finished within 6 months.

Club members and visiting teams have up to now had to change in their cars or the nearby community centre.

Cllr Ollie Crowe says it’s great news that this important facility for Hibernians is to be completed.