Galway City Council to ‘review’ Kirwan junction
Councillors are demanding proof that the €5 million spent to transform Kirwan Roundabout into a signalised junction was money well spent – blasting the new junction as having created long delays and worsening rat-running.
A meeting of the local authority last week heard that while there was a general acceptance there would be ‘teething problems’ with the traffic-light junction after it became operational in July, ongoing issues were continuing to draw the ire of road users and local residents.
Cllr Mike Cubbard (Ind) said he was one of five councillors on the previous Council to initially vote against the removal of the roundabout, based on fears that it would increase traffic through local residential areas – a fear that had been realised.
“What changes have been needed to be done since it went live,” asked the former Mayor, indicating that there had been little improvement.
Cllr Alan Cheevers (FF) said he understood that enhancement works were being done, but more were required.
“A lot of drivers are avoiding it and its driving traffic through the likes of Terryland Business Park. The Tuam Road is now gridlocked,” he said, calling on the Council to do a “PR exercise” to encourage drivers back to Kirwan.
Cllr Clodagh Higgins (FG) said the junction continued to confuse people and suggested that “overhead hanging signs” would be of assistance.
Green Party Councillor Niall Murphy said when the roundabout was slated for removal, it was promised that delays would be reduced by 25% and rat-running by 90% – but as yet, no evidence had been provided to show this.
“We need to put some science on this.
“The rat-running has moved to Dyke Road and there are some sections of that road where there are no footpaths, so it is quite dangerous for pedestrians,” said Cllr Murphy.
Acting Director of Services for Transport, Uinsinn Finn, told the meeting he believed there was a silent majority that were satisfied with the new junction.
He said that the junction’s ‘go live’ date was July 19, which coincided with the reopening of many parts of society that had been in lockdown due to Covid, and that had contributed to additional traffic.
“The first two objectives were to improve pedestrian and cyclist safety, and those objectives have been achieved.
“There will be a post project review – that is something that we always do and I would be happy to bring that back to Council for its consideration,” said Mr Finn.
Council Chief Executive Brendan McGrath confirmed that review was set to get underway.
“It will go through the various elements and if issues arise following the review, they will be addressed,” he said.